Route · Side-by-side migration
Build new, carry the configuration over, then move the VMs.
For an environment that goes to VCF or VVF 9 by building a new environment next to the old one instead of upgrading in place. Start with the overview: it helps you choose the route and walks through the phases. Upgrading in place instead? Pick the Full VCF or standalone VVF track.
The set, in phase order
Side-by-side migration docs
Overview: build new, then migrate
Build a new VCF or VVF 9 environment next to the old one, carry roles, tags, storage policies, folders and networks over, then migrate the VMs with or without HCX. Five questions to pick the route, seven phases each closed by a check.
OpenPhase 2: vCenter configuration
Phase 2 of a side-by-side migration, step by step: roles, tag categories and tags, custom attributes, storage policies, folders and permissions, resource pools and DRS rules, templates and content libraries, with the commands and a check after each step.
OpenPhase 3: networks and firewall
Phase 3 of a side-by-side migration, step by step: the network mapping table, VDS port groups, NSX segments and profiles, the NSX distributed firewall with Jeroen Buren's toolkit, and the services on the NSX gateways (NAT, load balancer, DHCP, DNS, VPN, gateway firewall), each with commands, undo and a check.
OpenPhase 4: prove the path
The gate before the first wave: every network flow tested from both ends with a command per flow, HCX diagnostics and Transport Analytics, a test VM there and back per route, the checks after each move, measured durations, and a signed evidence sheet.
OpenPhase 5: migrating without HCX
Advanced Cross vCenter vMotion in waves: which way to start a migration, sizing a wave, a five-step runbook per wave, encrypted VMs, VDS versions, EVC, and moving a VM back.
OpenPhase 5: migrating with HCX
HCX Mobility Groups in waves: a migration type per VM, what HCX carries over, sync and switchover windows, special cases, moving a VM back, and common migration errors. Building HCX stays in the deployment-planning guide.
OpenPhase 6: cutover and clean-up
Per network: what else still uses it, moving the gateway (HCX unextend with Connect cloud network, or the network team without HCX) and the checks after. Then repointing what still points at the source, removing HCX in the order Broadcom documents, and retiring the source after a quiet period.
Open